Install requirements.

AeroBarrier can be installed at the pre-drywall or post-drywall stage. Each stage has its own site conditions. Please review the section that applies to your project and share the checklist with your builder.

Stage 1

Pre-drywall

Seals the exterior envelope before insulation.

When this installation takes place

Immediately before insulation is installed, once all mechanical installation is complete. If any of the insulation is open- or closed-cell spray foam, AeroBarrier is best installed immediately after the spray foam and before any other insulation.

Conditions required

  • Unvented (conditioned) attic, or no attic (for example, a flat roof). If the attic is vented, a post-drywall installation is required.
  • Fully sheathed exterior. The building must be entirely sheathed with OSB or plywood. Where building paper is exposed from the interior, those areas must be sheathed, or a post-drywall installation is required.
  • Doors and windows installed, with all Title 24 foaming around them completed.
  • No large openings in the envelope that would require blocking or sheathing to close.
  • Penetrations foamed. All envelope penetrations (ducts, pipes and similar) must be sealed with a foam gun before we arrive. Our crew inspects the building and foams any that were missed. AeroBarrier can seal any hole under ½ inch, but large, easy-to-reach holes are sealed more economically with foam.
  • A blower door opening. We need a doorway no larger than 8 ft tall by 3 ft wide. Blower doors cannot be mounted in pivot doors.
Stage 2

Post-drywall

Seals the drywall air barrier before finishes.

When this installation takes place

Ideally at completion of drywall texture, after the drywall subcontractor has finished and before the painter primes. It can also take place after taping and mudding but before texture, after priming, or, if no other option is available, after painting. The sealant does not adhere to vertical surfaces other than at leakage points.

A post-drywall installation is required when the attic is vented. With an unvented attic or no attic, either stage works, so you can choose the one that suits your schedule.

Where a post-drywall installation is needed because of a vented attic, a hybrid approach is possible: only the ceiling drywall is hung, taped and mudded first. The ceiling isolates the attic, and one installation seals both the ceiling and the exterior walls.

Conditions required

  • Drywall hung, taped and mudded (or ceiling drywall only, for the hybrid approach above).
  • HVAC register boots caulked to the drywall, as required by California code.
  • No finishes installed.
  • Flush baseboards. Where baseboard will be flush with the drywall (for example, with a reveal), the opening below the drywall must be sealed with a membrane that remains in place. Please let us know in advance if your project uses this detail.
Both stages

On installation day.

  • Move all materials, supplies, equipment and tools away from exterior walls and cover them. Drape plastic over anything that must be protected from sealant settling out of the air.
  • After sealing, sealant settles onto the floors and leaves them slightly tacky. Most of the tackiness is gone by the next day, and it does not interfere with any type of flooring.
  • No other trades can work inside the building during installation. Trades working outside must keep the entrance clear for our trailer, equipment and crew.

Questions about your project's conditions? Contact us before scheduling.